The carpenter is nearing the end as the handrail went up yesterday and all of the holes were drilled for the black metal spindles which he will be putting in today. After that he just has a few odds and ends to wrap up which means he should be done no later than Wednesday.
The electricians were there yesterday hanging all of the lights and fans as well as installing all of the outlets and switches. They will be back today to finish up and then the drywallers come back to touch-up some spots and to finish the garage.

As for me, well, all of the stained trim got a couple of poly coats this past weekend and the painted trim is next to be touched-up before moving on to poly the stairs and railing sometime this weekend. After that the doors all come off and get painted and then it is on to hardwood flooring.

Still a good bit to do but the end.....for now...is certainly in sight!
Are you doing pickets on that handrail? that wouldn't pass code around here without the pickets every 4" on center. Looks great though.