The basement block is nearing completion.

We are getting closer to having the basement block all done. As of late yesterday the walkout area was pretty much done leaving only the south wall of the walkout and the garage left to do. The garage would be quick if it did not fall in a low spot causing it to be 10 course on the front side and 7 course on the back........YES, that is a lot of fill material!

The mason's are saying they will be done on Friday and the waterproofers will be next in-line, then I get to start rough grading and filling the garage. At this point, the framers are "scheduled" to begin on December 26th.